Pile Foundation Installation
Date
February 2026
Location
Wellington, New Zealand
Tascon built the foundation for a new billboard on Hut Road for Hanlon Industries. The job was a single 5 m deep pile at 1.05 m diameter, capped with a 1.5 m x 1 m pile cap set 1 m deep.
The site sat on reclaimed land, so groundwater was a real factor from the start. We drove the casing the full depth to keep the bore stable and worked through significant groundwater the whole way down. Access was tight, so the whole job ran on small plant. Cade and Valentin delivered it start to finish.